Bridge project in Monticello, IN.
EPS form liners to pour four piers
Piers ranged in height from 29’ to 43’
Superior Construction used .9 lb density EPS form liners to pour four piers for a new bridge project in Monticello, IN. The piers ranged in height from 29’ to 43’. Because the concrete was poured in short lifts the lighter density expanded polystyrene was able to be used.